Smartification works on the M27 at J4 has seen these columns on the left being disconnected from their supply, and they now have "DEAD" painted on their bases in green paint. The embankment behind them has been cleared and is being excavated back. The columns behind the camera have been rigged up with a new temporary supply connected via a waterproof box screwed to the base of the columns, with the supply cables running up the embankment in orange trunking.

On the other side of the carriageway all of these columns on the left are also marked "DEAD" except for the last 2 mounted on the edge of the retaining wall of the overbridge in the far distance. I suspect they are also disconnected, but are too high up to be marked.


Top
 Profile  Personal album 
 
PostPosted: Wed Nov 20, 2019 4:55 pm 
Offline
Site Administration
User avatar

Joined: Mon Nov 09, 2009 5:38 pm
Posts: 3217
Images: 27
Location: Salisbury
Further to my last, all the columns pictured here on the LHS carriageway, forward to where the lighting ends just before J5, have now been removed.


Top
 Profile  Personal album 
 
PostPosted: Thu Nov 28, 2019 6:57 pm 
Offline
Site Administration
User avatar

Joined: Mon Nov 09, 2009 5:38 pm
Posts: 3217
Images: 27
Location: Salisbury
The east side of J4 of the M27 is now unlit. All verge mounted columns have either been removed or disconnected. There is still working lighting on the slips to and from the M3, the central reservation lighting, west of the M3 north bound overbridge, is also still in place and working.


Top
 Profile  Personal album 
 
PostPosted: Mon Dec 23, 2019 8:19 pm 
Offline
Member
User avatar

Joined: Mon Nov 09, 2009 5:27 pm
Posts: 1685
Images: 200
In addition to a number of columns on the M3 which were found to have corroded mounting studs being chopped down, which were installed in around 1991/2, a number of columns on the M3/M27 link roads which are slightly newer (about 1994) have also been chopped. Lighting that only lasts 25 years before structural failure; that is very poor.


Top
 Profile  Personal album 
 
PostPosted: Thu Jan 02, 2020 2:52 pm 
Offline
Site Administration
User avatar

Joined: Mon Nov 09, 2009 5:38 pm
Posts: 3217
Images: 27
Location: Salisbury
A trip along this section at the end of of 2019,  showed that 26 columns have been removed from the central reservation, with 52  still standing, so a 3rd have been removed. Some dash cam footage, unfortunately the weather was dull and gloomy.

At the start of the lighting near J13, a large section with columns removed. Next central reservation columns are by the overhead gantry in the distance.

Image

Another section further south, with a big gap in the columns.

Image


Top
 Profile  Personal album 
 
PostPosted: Sun Jan 19, 2020 8:58 pm 
Offline
Site Administration
User avatar

Joined: Mon Nov 09, 2009 5:38 pm
Posts: 3217
Images: 27
Location: Salisbury
M27 J12 has seen more Lumas removed recently, presumably following more safety checks given the design flaw which causes them to fall from columns. Lanterns are missing from the twin bracket columns on the central reservation, as well as the single bracket columns on the link/slip roads.


Top
 Profile  Personal album 
 

Display posts from previous:  Sort by  


Post new topic Reply to topic  [ 56 posts ] 

All times are UTC



You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Jump to:  

Who is online

Users browsing this forum: No registered users and 3 guests



Search for: